We have detected that you are using a browser or version of a browser which is not supported.   To get the best experience using EARS 2 we recommend that you install a version from the supported browser list available on the  DEMIRS website.  
Environmental Assessment and Regulatory System
Annual Environmental Report Compliance Reporting
Reference ID: AER-661-16644
Period Finish: Sep/2016
Status: Submitted
Project: J00751 Tallering Peak / Mt Gibson
-> Environmental Group Site (Site):
S0020232 Tallering Peak Group


Are you sure you want to lock this MRF Submission?

Are you sure you want to unlock this MRF Submission?

Step 1 Report Details
Company / Individual Details

MOUNT GIBSON MINING Limited
Site Details

J00751

Tallering Peak / Mt Gibson

S0020232

Tallering Peak Group
Report Period

Oct/2015

Sep/2016
Step 3.1 Environmental Group Site - Site Activity Summary
Guidance

Provide a summary of the following for the AER reporting period:

  • The status of the site
  • exploration activities
  • operational mining activities
  • rehabilitation activities
  • progress towards mine closure (e.g. research / trials undertaken, progress with closure plan)
  • progress against the care and maintenance plan (if applicable*)

Attach supporting information in the Attach Documents section.

*   Sites on care and maintenance require a care and maintenance plan. For more information, refer to section 88 of the Mine Safety and Inspection Act 1994 and the worksheet
http://www.dmp.wa.gov.au/Documents/Environment/ENV-MEB-221.pdf
.

Site Activity Summary

MGM's Tallering Peak minesite ended iron ore mining in late May 2014. Progressive rehabilitation of the site began in 2008.  The remnant low grade stockpiles (4.0ha) and a portion of the haul road (4.63ha) remain to be rehabilitated in early 2017.  These remaining rehabilitation areas represent 2% of the overall disturbance across all tenements at the minesite.  Besides the remaining 2% of remaining land area to be rehabilitated, all areas of the minesite are now classified as Land to be assessed and signed off by DMP as "Rehabilitated Land".

 

Tenements M70/1063, M70/1064 and G70/193 were approved by the DMP for relinquishment on 8 July 2016.   Table 1 contains a summary of progress towards agreed completion criteria for Tallering Peak.   A case for relinquishment of the remaining tenements associated with the minesite will be submitted to the DMP in mid-2017.

 

During the reporting period, stockpiles of low grade lump and fines were transported from the loadout area to Geraldton port for export.  The remaining low grade fines will be transported to Geraldton port by early-2017.  Following final transport of the low grade fines, the area will be re-contoured, cross ripped and seeded in accordance with standard site procedures.

 

All infrastructure and developed land at the Ruvidini rail transfer facility in Mullewa (30.91ha) will remain for the short to medium term.  This facility has been in care and maintenance since late 2014.  Future uses for the site are still being evaluated.

 

Version 9.0 of the Tallering Peak Mine Closure Plan (MCP) was approved on 16 February 2015.  Version 10.0 of the MCP was submitted to the DMP on 31 October 2016.

  


Attached Documents
Authorised for Public Release File Name File Size Description
Yes AppA_Progress Table.pdf 153 KB Table 1 - Completion Criteria Progress Summary
Step 3.2 Environmental Group Site - Site Summary Table
Guidance

Provide a concise overview of the operations and the progress of closure planning for the Environmental Group Site.

Site Status

Rehabilitating & Monitoring

IRON ORE

2003

22

0
1
444.6900
1
39.5400


1 Value calculated from the information supplied in Step 3.4 Area of Activity.
Materials Balance
Total (m3 or tonnes) Comments
Volume of Material Mined:
Plant Throughput:
Volume of Waste Rock: 62,797,136 m3
Volume of Topsoil: 0 m3
Volume of Other Growth Medium2: 0 m3
Volume of Suitable Capping Material: 20,000 m3


2 An alternative "growth medium" may be required where topsoil is either not naturally present in adequate volumes to address rehabilitation requirements, or was not preserved (e.g. stripped and stockpiled) prior to mining.
Bond

$0.00
Total bond amount calculated from tenements listed in Step 2. Review Tenements
Closure Plan

Decommissioning

Yes


31/10/2014


Yes


16/02/2015


Step 3.3 Environmental Group Site - Site Plan
Guidance

A Site Plan must be attached that clearly and accurately reflects the information provided in this AER. The minimum requirements for the Site Plan are:

  • All operations and areas disturbed should be drawn on the plan with the scale and legend clearly shown
  • All tenements and their boundaries indicated
  • Include topographical, mine-site infrastructure details and cadastral information
  • Include areas rehabilitated to date with year completed and rehabilitation stage
  • Show areas disturbed during the reporting period
  • Show areas proposed for disturbance during the following reporting period

The Site plan will be publically available via the department's website. Please attach both a public and full version of the site plan if your main document contains confidential information.

Attached Site Plans
Authorised for Public Release File Name File Size Description
Yes MGI-TP-2016-AER-f01.pdf 4 MB Site Plan
Step 3.4 Environmental Group Site - Area of Activity
Guidance

All mining related disturbance and rehabilitation activity present at the end of the AER reporting period needs to be reported.

Enter a summary of how the area data was verified (e.g. orthophotography, surveying), click the Save Form button, then review and update the activities, disturbance and rehabilitation data for each tenement.

Data Verification Method

Disturbance data has been verified through a combination of orthophotography generated in late-2014 and surveying where new rehabilitation has occured since the spatial data was collected. Several assets have been transferred to the Wandina Station pastoral lease holder via a legal agreement. Therefore no further rehabilitation is required on these assets, such as bitumen access roads, previous camp areas for use as stock yards and fencing.

Tenement Activity Summary
Tenement Assessment Date Area Approved (ha) Total Area of Activity (ha) Land Under Rehabilitation (ha) Relinquished (ha) Disturbance (ha)
Reporting Period Change Stage 1 Stage 2 Total Rehab
G 70/192 30/09/2016 7.9600 7.9600 0.0000 0.0000 7.9600 7.9600 0.0000 0.0000
G 70/201 30/09/2016 2.0000 2.0000 0.0000 0.0000 0.0000 0.0000 0.0000 2.0000
G 70/202 30/09/2016 4.2800 4.2800 0.0000 0.0000 0.0000 0.0000 0.0000 4.2800
G 70/203 30/09/2016 5.1000 5.1000 0.0000 0.0000 0.0000 0.0000 0.0000 5.1000
G 70/204 30/09/2016 5.1800 5.1800 0.0000 0.0000 0.0000 0.0000 0.0000 5.1800
G 70/205 30/09/2016 2.3500 2.3500 0.0000 0.0000 0.0000 0.0000 0.0000 2.3500
L 70/60 30/09/2016 7.7000 7.7000 0.0000 0.0000 7.7000 7.6000 0.0000 0.0000
L 70/69 30/09/2016 1.3000 1.3000 0.0000 0.0000 1.3000 1.0000 0.0000 0.0000
L 70/73 30/09/2016 6.0000 6.0000 0.0000 0.0000 0.0000 0.0000 0.0000 6.0000
L 70/74 30/09/2016 6.0000 6.0000 0.0000 0.0000 0.0000 0.0000 0.0000 6.0000
M 70/1062-I 30/09/2016 3.0400 3.0400 0.0000 0.0000 3.0400 0.7600 0.0000 0.0000
M 70/896-I 30/09/2016 393.7800 393.7800 0.0000 0.0000 385.1500 372.8500 0.0000 8.6300
Total 444.6900 444.6900 0.0000 0.0000 405.1500 390.1700 0.0000 39.5400

Detailed Assessment Information

Tenement: G 70/192 (3 Activities)
Mine Activity Type Mine Activity Reference Area Approved Total Area of Activity (ha) Land Under Rehabilitation (ha) Relinquished Disturbance (ha)
Area as of Previous reporting period Area as of Current reporting period Change Stage 1 Stage 2 Total
Sewage pond Sewage Treatment 3.1200 3.1200 3.1200 0.0000 0.0000 3.1200 3.1200 0.0000 0.0000
Building (other than workshop) or camp site Camp 3.8200 3.8200 3.8200 0.0000 0.0000 3.8200 3.8200 0.0000 0.0000
Transport or service infrastructure corridor Access Road 1.0200 1.0200 1.0200 0.0000 0.0000 1.0200 1.0200 0.0000 0.0000
Total 7.9600 7.9600 7.9600 0.0000 0.0000 7.9600 7.9600 0.0000 0.0000
There is no assessment information to report on this tenement.
Tenement: G 70/201 (1 Activity)
Mine Activity Type Mine Activity Reference Area Approved Total Area of Activity (ha) Land Under Rehabilitation (ha) Relinquished Disturbance (ha)
Area as of Previous reporting period Area as of Current reporting period Change Stage 1 Stage 2 Total
Transport or service infrastructure corridor Access Road 2.0000 2.0000 2.0000 0.0000 0.0000 0.0000 0.0000 0.0000 2.0000
Total 2.0000 2.0000 2.0000 0.0000 0.0000 0.0000 0.0000 0.0000 2.0000
There is no assessment information to report on this tenement.
Tenement: G 70/202 (3 Activities)
Mine Activity Type Mine Activity Reference Area Approved Total Area of Activity (ha) Land Under Rehabilitation (ha) Relinquished Disturbance (ha)
Area as of Previous reporting period Area as of Current reporting period Change Stage 1 Stage 2 Total
Transport or service infrastructure corridor Railway corridor 0.2600 0.2600 0.2600 0.0000 0.0000 0.0000 0.0000 0.0000 0.2600
Transport or service infrastructure corridor Access Road 0.9500 0.9500 0.9500 0.0000 0.0000 0.0000 0.0000 0.0000 0.9500
Laydown or hardstand area Railhead Ore Stockpiles 3.0700 3.0700 3.0700 0.0000 0.0000 0.0000 0.0000 0.0000 3.0700
Total 4.2800 4.2800 4.2800 0.0000 0.0000 0.0000 0.0000 0.0000 4.2800
There is no assessment information to report on this tenement.
Tenement: G 70/203 (3 Activities)
Mine Activity Type Mine Activity Reference Area Approved Total Area of Activity (ha) Land Under Rehabilitation (ha) Relinquished Disturbance (ha)
Area as of Previous reporting period Area as of Current reporting period Change Stage 1 Stage 2 Total
Transport or service infrastructure corridor Railway corridor 0.1900 0.1900 0.1900 0.0000 0.0000 0.0000 0.0000 0.0000 0.1900
Transport or service infrastructure corridor Access Road 1.0300 1.0300 1.0300 0.0000 0.0000 0.0000 0.0000 0.0000 1.0300
Laydown or hardstand area Railhead Ore Stockpiles 3.8800 3.8800 3.8800 0.0000 0.0000 0.0000 0.0000 0.0000 3.8800
Total 5.1000 5.1000 5.1000 0.0000 0.0000 0.0000 0.0000 0.0000 5.1000
There is no assessment information to report on this tenement.
Tenement: G 70/204 (3 Activities)
Mine Activity Type Mine Activity Reference Area Approved Total Area of Activity (ha) Land Under Rehabilitation (ha) Relinquished Disturbance (ha)
Area as of Previous reporting period Area as of Current reporting period Change Stage 1 Stage 2 Total
Transport or service infrastructure corridor Railway corridor 0.2300 0.2300 0.2300 0.0000 0.0000 0.0000 0.0000 0.0000 0.2300
Transport or service infrastructure corridor Access Road 2.0200 2.0200 2.0200 0.0000 0.0000 0.0000 0.0000 0.0000 2.0200
Laydown or hardstand area Railhead Ore Stockpiles 2.9300 2.9300 2.9300 0.0000 0.0000 0.0000 0.0000 0.0000 2.9300
Total 5.1800 5.1800 5.1800 0.0000 0.0000 0.0000 0.0000 0.0000 5.1800
There is no assessment information to report on this tenement.
Tenement: G 70/205 (3 Activities)
Mine Activity Type Mine Activity Reference Area Approved Total Area of Activity (ha) Land Under Rehabilitation (ha) Relinquished Disturbance (ha)
Area as of Previous reporting period Area as of Current reporting period Change Stage 1 Stage 2 Total
Workshop Sheds and offices 0.5200 0.5200 0.5200 0.0000 0.0000 0.0000 0.0000 0.0000 0.5200
Transport or service infrastructure corridor Railway corridor 0.4900 0.4900 0.4900 0.0000 0.0000 0.0000 0.0000 0.0000 0.4900
Transport or service infrastructure corridor Access Road 1.3400 1.3400 1.3400 0.0000 0.0000 0.0000 0.0000 0.0000 1.3400
Total 2.3500 2.3500 2.3500 0.0000 0.0000 0.0000 0.0000 0.0000 2.3500
There is no assessment information to report on this tenement.
Tenement: L 70/60 (2 Activities)
Mine Activity Type Mine Activity Reference Area Approved Total Area of Activity (ha) Land Under Rehabilitation (ha) Relinquished Disturbance (ha)
Area as of Previous reporting period Area as of Current reporting period Change Stage 1 Stage 2 Total
Transport or service infrastructure corridor Access Road 7.6000 7.6000 7.6000 0.0000 0.0000 7.6000 7.6000 0.0000 0.0000
Exploration/Prospecting Operations - Land (other than land under rehabilitation or rehabilitated land) that has been disturbed by exploration operations Tracks 0.1000 0.1000 0.1000 0.0000 0.0000 0.1000 0.0000 0.0000
Total 7.7000 7.7000 7.7000 0.0000 0.0000 7.7000 7.6000 0.0000 0.0000
There is no assessment information to report on this tenement.
Tenement: L 70/69 (3 Activities)
Mine Activity Type Mine Activity Reference Area Approved Total Area of Activity (ha) Land Under Rehabilitation (ha) Relinquished Disturbance (ha)
Area as of Previous reporting period Area as of Current reporting period Change Stage 1 Stage 2 Total
Transport or service infrastructure corridor Freshwater pipeline 0.3000 0.3000 0.3000 0.0000 0.0000 0.3000 0.3000 0.0000 0.0000
Transport or service infrastructure corridor Access Road 0.7000 0.7000 0.7000 0.0000 0.0000 0.7000 0.7000 0.0000 0.0000
Exploration/Prospecting Operations - Land (other than land under rehabilitation or rehabilitated land) that has been disturbed by exploration operations Tracks 0.3000 0.3000 0.3000 0.0000 0.0000 0.3000 0.0000 0.0000
Total 1.3000 1.3000 1.3000 0.0000 0.0000 1.3000 1.0000 0.0000 0.0000
There is no assessment information to report on this tenement.
Tenement: L 70/73 (1 Activity)
Mine Activity Type Mine Activity Reference Area Approved Total Area of Activity (ha) Land Under Rehabilitation (ha) Relinquished Disturbance (ha)
Area as of Previous reporting period Area as of Current reporting period Change Stage 1 Stage 2 Total
Transport or service infrastructure corridor Access Road 6.0000 6.0000 6.0000 0.0000 0.0000 0.0000 0.0000 0.0000 6.0000
Total 6.0000 6.0000 6.0000 0.0000 0.0000 0.0000 0.0000 0.0000 6.0000
There is no assessment information to report on this tenement.
Tenement: L 70/74 (1 Activity)
Mine Activity Type Mine Activity Reference Area Approved Total Area of Activity (ha) Land Under Rehabilitation (ha) Relinquished Disturbance (ha)
Area as of Previous reporting period Area as of Current reporting period Change Stage 1 Stage 2 Total
Transport or service infrastructure corridor Access Road 6.0000 6.0000 6.0000 0.0000 0.0000 0.0000 0.0000 0.0000 6.0000
Total 6.0000 6.0000 6.0000 0.0000 0.0000 0.0000 0.0000 0.0000 6.0000
There is no assessment information to report on this tenement.
Tenement: M 70/1062-I (3 Activities)
Mine Activity Type Mine Activity Reference Area Approved Total Area of Activity (ha) Land Under Rehabilitation (ha) Relinquished Disturbance (ha)
Area as of Previous reporting period Area as of Current reporting period Change Stage 1 Stage 2 Total
Waste dump or overburden stockpile (class 1) Abandonment bund sth of Tallering Trig 0.2000 0.2000 0.2000 0.0000 0.0000 0.2000 0.2000 0.0000 0.0000
Transport or service infrastructure corridor Access Road 0.5600 0.5600 0.5600 0.0000 0.0000 0.5600 0.5600 0.0000 0.0000
Exploration/Prospecting Operations - Land (other than land under rehabilitation or rehabilitated land) that has been disturbed by exploration operations Tracks 2.2800 2.2800 2.2800 0.0000 0.0000 2.2800 0.0000 0.0000
Total 3.0400 3.0400 3.0400 0.0000 0.0000 3.0400 0.7600 0.0000 0.0000
There is no assessment information to report on this tenement.
Tenement: M 70/896-I (12 Activities)
Mine Activity Type Mine Activity Reference Area Approved Total Area of Activity (ha) Land Under Rehabilitation (ha) Relinquished Disturbance (ha)
Area as of Previous reporting period Area as of Current reporting period Change Stage 1 Stage 2 Total
Waste dump or overburden stockpile (class 1) T4 Waste Dump 65.3000 65.3000 65.3000 0.0000 0.0000 65.3000 65.3000 0.0000 0.0000
Waste dump or overburden stockpile (class 1) T3/T5/T6 Waste Dump 165.0000 165.0000 165.0000 0.0000 0.0000 165.0000 165.0000 0.0000 0.0000
Dam - saline water or process liquor Turkeys nest dams 0.5000 0.5000 0.5000 0.0000 0.0000 0.5000 0.5000 0.0000 0.0000
Plant site ROM & Crusher 18.7700 18.7700 18.7700 0.0000 0.0000 14.7700 14.7700 0.0000 4.0000
Mining void (with a depth of at least 5 metres) - below ground water level T5 Pit 16.0000 16.0000 16.0000 0.0000 0.0000 16.0000 16.0000 0.0000 0.0000
Mining void (with a depth of at least 5 metres) - below ground water level T6 Pit 63.0000 63.0000 63.0000 0.0000 0.0000 63.0000 63.0000 0.0000 0.0000
Building (other than workshop) or camp site Admin area workshops and fuel farm 8.4400 8.4400 8.4400 0.0000 0.0000 8.4400 8.4400 0.0000 0.0000
Transport or service infrastructure corridor Freshwater pipeline 1.6000 1.6000 1.6000 0.0000 0.0000 1.6000 1.6000 0.0000 0.0000
Transport or service infrastructure corridor Haul Roads 32.1200 32.1200 32.1200 0.0000 0.0000 27.4900 27.4900 0.0000 4.6300
Mining void (with a depth of at least 5 metres) - above ground water level T1 Pit 8.2200 8.2200 8.2200 0.0000 0.0000 8.2200 8.2200 0.0000 0.0000
Laydown or hardstand area Laydown Areas 2.5300 2.5300 2.5300 0.0000 0.0000 2.5300 2.5300 0.0000 0.0000
Exploration/Prospecting Operations - Land (other than land under rehabilitation or rehabilitated land) that has been disturbed by exploration operations Tracks 12.3000 12.3000 12.3000 0.0000 0.0000 12.3000 0.0000 0.0000
Total 393.7800 393.7800 393.7800 0.0000 0.0000 385.1500 372.8500 0.0000 8.6300
There is no assessment information to report on this tenement.